Published:2021-06-28
According to Cai Kelin, Director of the Early Intervention Office of New Passenger Dedicated Line of China Railway Harbin Group Co., Ltd., during the integrated commissioning & test period, accurate tests will be carried out on 99 items of 11 disciplines along the whole line, such as track, bridge and signal.
The Mudanjiang-Jiamusi HSR, located in the extremely cold area of China, is a key railway project in the National 13th Five-Year Plan and a major construction project in the Mid-and-Long-Term Railway Network Plan. The railway is located in the eastern part of Heilongjiang, passes through 5 prefecture-level cities and 2 county-level administrative districts including Mudanjiang City, Linkou County, Jixi City, Qitaihe City, Huanan County, Shuangyashan City and Jiamusi City. It has a design speed of 250 km/h and a total length of 371.6 km, standing as the longest HSR line in Heilongjiang Province so far.