Mudanjiang-Jiamusi High Speed Railway Fully Enters Integrated Commissioning & Test Stage

Published:2021-06-28

  At 8:28 on June 10, as the first inspection train departed from Mudanjiang Station to Jiamusi, the new Mudanjiang-Jiamusi HSR officially entered the integrated commissioning & test stage, which is the key period of project acceptance.

  According to Cai Kelin, Director of the Early Intervention Office of New Passenger Dedicated Line of China Railway Harbin Group Co., Ltd., during the integrated commissioning & test period, accurate tests will be carried out on 99 items of 11 disciplines along the whole line, such as track, bridge and signal.

  The Mudanjiang-Jiamusi HSR, located in the extremely cold area of China, is a key railway project in the National 13th Five-Year Plan and a major construction project in the Mid-and-Long-Term Railway Network Plan. The railway is located in the eastern part of Heilongjiang, passes through 5 prefecture-level cities and 2 county-level administrative districts including Mudanjiang City, Linkou County, Jixi City, Qitaihe City, Huanan County, Shuangyashan City and Jiamusi City. It has a design speed of 250 km/h and a total length of 371.6 km, standing as the longest HSR line in Heilongjiang Province so far.